Reducing SLU Scheduling Issues

Installing Self-Leveling Underlayment Faster And More Efficiently

Introduction

With ever-growing pressures to complete buildings on tight schedules, flooring and subflooring contractors often feel pinched from multiple sources. Modern flooring materials such as tiling and the associated adhesives are advancing to dry faster than before, and various construction trades demand access to rooms sooner.

Owners, designers and general contractors demand high quality, along with rapid installation. For contractors installing self-leveling underlayment (SLU), this means new approaches are needed to complete work faster and more efficiently. Pumping of SLU can help address these challenges.

 

50k Square Feet in One Day

A New Approach

With SLU pumping, scheduling challenges can be greatly reduced. Placement can generally be completed faster with fewer people. Since larger rooms do not necessarily require additional workers, these resources can be applied elsewhere on the project or on other projects.

Time savings begin with the material mixing process. Using combined mixing and pumping units such as the Graco Toughtek MP20, water can be mixed automatically with cement-aggregate compounds in prescribed amounts. SLU mixtures can be pumped up to distances of 300 feet and heights of 60 feet.

In addition to time savings and simplified batch placement, SLU pumping can simplify setup and equipment transportation. The MP40 (a larger version of the MP20) is approximately 64 inches long, 32 inches wide and 53 inches tall, so it can typically be loaded and transported in a standard pickup truck. With built-in wheels, it can be transported around a job site easily.

 

Pumping self leveling underlayment

Simplified, continuous placement of SLU

Coordination of batch placement is another challenge greatly simplified with pumped SLU. Instead of manually placing batches that must be matched and tied together, pumped SLU can be placed in a more continuous manner, with multiple passes made in a zig-zag pattern, as shown in Figure 3. This enables workers to place SLU in widths of just a few inches at a time, or several feet at a time, while maintaining a “wet edge” and more continuity in the SLU layer.

In addition to time savings and simplified batch placement, SLU pumping can simplify setup and equipment transportation. The MP40 (a larger version of the MP20) is approximately 64 inches long, 32 inches wide and 53 inches tall, so it can typically be loaded and transported in a standard pickup truck. With built-in wheels, it can be transported around a job site easily. 

The automated approach also improves mix consistency and placement precision. With water flow rates set according to manufacturer’s recommendations, compound materials and water can be mixed within the mixing chamber at the same rate all day long. The units can be used to correct uneven floors, repair damaged concrete, and provide a smooth surface for carpet, tile or other floor covering.

While skilled workers are still needed to place SLU, skill sets from other crafts are often transferrable. Crews that can place stucco can generally place SLU. Daily profits can be substantially higher when pumping SLU, when compared to pumping other types of mortar products. Some examples clarify how this works.

 

Self-leveling underlayment placement patterns

Stucco Vs SLU Pumping

Consider a typical day of pumping stucco versus a typical day of pumping an SLU overlay. Assuming an 8-hour day, the cost breakdown might look something like this:

 

Stucco (500 Square Yards, 1/2-Inch Basecoat)

Labor: 6 workers x 8 hrs @ $40/hr = $1,920

Materials: 500 sq yds / 3 sq yds/bag x $6.20/bag = $1,033

Subtotal = $2,953

40% overhead & profit = $1,181

 

SLU (16,250 Square Feet, 1/4-Inch Overlay)

Labor: 6 workers x 8 hrs @ $40.00/hr $1,920

Materials: 6.5 hrs x 100 bags/hr x $20.00/bag = $13,000

Subtotal: $14,920

40% overhead & profit = $5,968

In the above scenario, the potential gross profit for a given day of pumping SLU is five times that of the same day pumping stucco.  This is a very conservative estimate, as some mixing pumps can mix and place 200 bags per hour. 

 

SLU Pumping Vs Manual Placement

As another example, assume two crews of six persons each, with one crew pumping SLU and the other placing SLU manually.  The individual roles might be as follows:

 

Mixing Pump

  • 2 people taking turns breaking sacks into mixing pump hopper
  • 1 person managing excess hose as the room is poured from the furthest point
  • 1 person holding the end of the hose controlling placement of mixed material
  • 1 person on gauge rake
  • 1 person with smoother trowel  

 

Hippo Drill/Barrel Mixers (2 Mixing Units)

  • 4 people for breaking bags, adding water, mixing and wheeling mixed material into place
  • 1 person on gauge rake
  • 1 person with smoother trowel

The pumping crew can mix and place approximately 200 sacks per hour.  This equates to 1300 sacks, or 32,500 square feet at ¼-inch thickness, for an average day of 6.5 hours of actual pumping. 

The manual crew, at an average of five bags in 7 minutes per barrel, can mix and place 90 sacks per hour.  This equates to 585 sacks, or 14,265 square feet at ¼-inch thickness for the same 6.5 hours of pumping. 

Based on these parameters, a pumping crew can apply more than twice the square footage in a given day. This is accomplished while working at a smooth constant pace, placing consistently mixed material, and not overworking personnel.  Assuming a markup for SLU toppings of $.50 per square foot and a typical eight-hour day (6.5 mixing hours), this can equate to nearly $10,000 per day in added profits.

Have Questions? Let's Talk.

Contact an Expert

Contact an Expert

We'll help you choose the right product for your job.

Tech Support

Tech Support

Monday-Friday
7:30 a.m.-5 p.m. Central Time

Email Support

Email Support

Graco